In 2024, Acc Bau completed three wind farm projects in Germany, involving a total of 11 wind turbines.

One of the most notable achievements was the construction of a wind turbine foundation in Hoort, where an exceptional engineering solution was applied. The anchor cage of the foundation reached a height of 9 meters, with the turbine positioned at the same level. This presented a significant engineering challenge, requiring advanced construction techniques and expertise.

Our scope of work included:

  • Earthworks, including soil replacement,
  • Installation of the anchor cage with precise leveling,
  • Comprehensive construction of the foundation, including material supply,
  • Construction of the assembly area,
  • Installation of the foundation grounding system with measurements,
  • Construction of temporary work surfaces.

Acc Bau acted as the general contractor for this project and the other wind farm projects in Germany, delivering comprehensive services and ensuring the highest standards of quality.

We take pride in contributing to the development of renewable energy in Europe.

We invite you to collaborate with us on future projects!

 

 


ACC BAU Aleksander Czarnecki

ul. Radosna 1
62-040 Puszczykowo
Let’s connect on:
Our website uses cookies to ensure top quality of the services you receive in a way customised to your needs. If you do not change your cookies settings, you agree to have them saved on your end device. For further details, see the PRIVACY AND COOKIES POLICY. Accept